HOW TO PREPARE VALUATION REPORT OF N.A. PLOT & EXISTING BUILDING
VALUATION REPORT OF N.A PLOT & EXISTING BUILDING
--------------------------------------------------------------------------------------------
A) Name of the Property Holder: Owner Name
B) Location of Land: Address of Site / Building
C) Type of Land: N.A Site with Existing Building
D) Land/Site Area : : 0 Acres & 1 Guntas 14.75 Anna = 1665 Sq.ft
E) Market Value: 2700 Rs/ Sq.ft
F) Total Cost of Site = Total Site Area X Market Value
= 1665 Sq.ft X 2700 Rs / Sq.ft = 44,95,500 /-
G) Builtup Area of Existing Building : 803.3 Sq.ft
H) Present Construction Cost = 2200 Rs / Sq.ft
I) As Building is built in the year 1996, it’s been 24 Years,
Construction Cost after depreciation of 20 % = 1830 Rs / Sq.ft
J) Total Valuation of Building = Total Builtup Area X Construction Cost
= 803.3 Sq.ft X 1830 Rs / Sq.ft = 14,70,039 /-
Total Cost of Site & Existing Building ( F + J) = 59, 65,539/-
SAY RS: 59, 66,000/-
(RUPEES FIFTY NINE LAKHS AND SIXTY SIX THOUSANDS ONLY)